Lameco junction, Osogbo · evidence 2026-07-01
Lameco Flyover Bridge
Official state report says commissioned 1 July 2026
- Officeholder at evidence
- Ademola Adeleke
- Delivery agency / contractor
- Osun State Government / Ministry of Works
- Verified lifetime actual spending
- Not established in this file
- Official claim and event photos are not an independent engineering audit.
- No contract amount or final paid total established.
- July evidence does not establish present bridge condition; maintenance and vandalism require separate dated observations.
Dated condition photographs at source
Publisher photographs linked from this project evidence page; inspect individual image before display · capture date unavailable ↗Source photographs are linked with their dates. They do not establish today’s condition. Reuse permission has not been confirmed.