Make room for trade.
Tema Terminal 3
Ghana’s expanded container terminal shows how a port investment can be examined against capacity and actual service performance.
- COST · US DOLLARS
- US$1.5BPPP project estimate · 2024US$1.5 billion — estimated project cost in Ghana’s 2024 PPP report. Estimate, not audited final spend.
- THE TIMELINE
- Phases one and two commissioned 13 November 2025
- WHAT WAS BUILT
- 3 million TEU/year — reported capacity, not throughput.
Open the evidence file 2 sources ↗
- Who owns / delivers it?
- MPS concession; GPHA 30% equity, reported in the 2024 finance ministry PPP report.
- Reported activity
- 2024 import-truck turnaround: 90 minutes against a 60-minute target. Export trucks: 40 minutes against a 90-minute target.
- What still needs checking?
- A public-private concession with different phases. Cost is estimated; scanner breakdowns contributed to the missed import target.
- Ghana Ministry of Finance — printed pp. 64–65 ↗Published: 2024 reporting year
- Ministry of Transport — commissioning ↗Published: 2025-11-13
Source-linked record · record review: 2026-10-13. Dates and costs retain the original source’s scope; this preview does not certify an audit.