Tema Terminal 3
Phases one and two commissioned 13 November 2025
- Ownership / delivery
- MPS concession; GPHA 30% equity, reported in the 2024 finance ministry PPP report.
- Cost and scope
- US$1.5 billion estimated project cost — 2024 PPP report.
- Capacity / infrastructure
- 3 million TEU/year — reported capacity, not throughput.
- Reported activity
- 2024 import-truck turnaround: 90 minutes against a 60-minute target. Export trucks: 40 minutes against a 90-minute target.
Comparison limits
A public-private concession with different phases. Cost is estimated; scanner breakdowns contributed to the missed import target.
Original records and source media
- Ghana Ministry of Finance — printed pp. 64–65 ↗2024 reporting year
- Ministry of Transport — commissioning ↗2025-11-13
Photographs/video remain on their original source pages. Reuse licences are not established, so source media is linked rather than copied.